Trench fill, strip, raft or piled foundations: which does your extension need?
The ground decides the foundation. On London Clay, trench fill is the usual answer, until trees or soft ground make it too deep.
Deciding what to do? This guide explains the background. For short answers on what to do next and what it costs, see quick answers.
The short answer
Most London extensions on clay use trench fill foundations: a narrow trench filled with concrete almost to ground level, usually at least about 1 m deep and deeper near trees. Strip footings are a shallower traditional alternative on firmer ground. A raft suits soft or variable ground where loads need spreading. Piles take loads down to deep, stable ground and become economical when trench fill would need to go very deep, often around 2.5 to 3 m or more.
Side by side
| Trench fill | Strip | Raft | Piled | |
|---|---|---|---|---|
| How it works | Trench filled with concrete almost to the surface | Concrete strip at the base, masonry up to ground | Reinforced slab spreading load over the whole footprint | Piles to deep ground with a beam or slab on top |
| Suits | Clay, most domestic extensions | Firm, non-shrinkable ground | Soft or variable ground, light buildings | Deep clay near trees, heave risk, poor made ground |
| Typical depth | About 1 m on clay, deeper near trees | Shallower | Near the surface | Many metres |
| Watch out for | Drains and services in the trench; tree heave | Clay shrinkage | Design and reinforcement detail | Cost and rig access |
What decides the choice
Four things: the soil and how shrinkable it is, nearby trees (including neighbours' and street trees), drains and sewers along the line of the foundation, and how soft or variable the ground is. On clay near trees, established depth guidance relates the required depth to the tree's species, height and distance. Where trees have been removed, the clay can swell, so the design may need compressible material against the foundation. See London Clay, trees and foundations.
Verdict
Trench fill for most clay sites. Strip on firm, non-shrinkable ground. Raft where ground is soft or variable and loads are light. Piles where trench fill would be very deep or heave is a risk. A trial pit or desk study early avoids redesigning in the trench.
Frequently asked questions
Can Building Control change my foundation depth on site?
Building Control inspects the excavation and can ask for it to go deeper if the ground isn't as expected, which is why the design should allow for what might be found.
What if a drain runs along the trench?
The foundation may need to go deeper, bridge over the drain or the drain may need diverting; Thames Water approval is needed near public sewers.
Do I need a ground investigation for a small extension?
Not always. A trial pit is often enough; a fuller investigation is worth it for soft ground, basements or new homes.
References
- NHBC Standards, Chapter 4.2, Building near trees
- Approved Document A (Structure), Building Regulations 2010
- BS EN 1997 (Eurocode 7, geotechnical design)