Building Control and problems on site: what to do next
Short answers for when approval is missing, someone needs more information, or something on site doesn't match the drawings.
A general guide, not a diagnosis. These answers describe common patterns. Only an inspection can say what is happening in your building. If you are worried about safety, call 020 3818 1115, or 07778 009449 out of hours.
Questions on this page
- We took out a wall years ago and never got Building Control approval. How can we sort it out now?
- My freeholder wants structural calculations before I can refurbish my flat. What should I send?
- Building Control says the builder's drawings aren't enough. What information is missing?
- My neighbour's Party Wall surveyor has asked for more details about the steel and foundations. Who provides them?
- The builder wants to swap the specified steel for one they can get sooner. Who should approve the change?
- Who checks the temporary props before a load-bearing wall comes down?
- We've opened the ceiling and the joists run the opposite way to the drawings. What happens now?
- Can an engineer check the steelwork before the builder covers it up?
- Our engineer has stopped responding and the build is halfway through. Can someone take over?
- Do I need a structural engineer's inspection as well as a Building Control visit?
We took out a wall years ago and never got Building Control approval. How can we sort it out now?
Apply to your council for a regularisation certificate: an engineer assesses the work and provides calculations, the council inspects, and some opening up is usually needed so hidden parts can be seen.
Regularisation is handled by the local authority, not a private building control body. See retrospective Building Regulations approval.
Next step Book a retrospective structural assessment (from £600 + VAT).
My freeholder wants structural calculations before I can refurbish my flat. What should I send?
Usually the engineer's calculations and drawings for any structural change, and sometimes a short design statement or method statement explaining how the work will be done safely.
Ask the freeholder or managing agent for their checklist. Many also want the contractor's insurance and a schedule of works.
Next step Book a structural design statement (from £450 + VAT) with the design, or a letter of comfort (from £300 + VAT).
Building Control says the builder's drawings aren't enough. What information is missing?
Usually the structural calculations and drawings that prove each beam, lintel, joist and foundation can carry its load, which Building Control needs under Part A.
See What are structural calculations? for what a package contains.
Next step Send us the Building Control letter and we'll tell you what is needed and quote.
My neighbour's Party Wall surveyor has asked for more details about the steel and foundations. Who provides them?
Your structural engineer: the surveyor needs the calculations and drawings showing how beams bear on the party wall and how foundations relate to the neighbour's.
Providing them early avoids delays to the party wall award. See the Party Wall Act and structural works.
Next step Our designs include party wall details; for an existing design, ask about a design revision (from £150 + VAT).
The builder wants to swap the specified steel for one they can get sooner. Who should approve the change?
The engineer who designed it: a substitute section must be checked by calculation, and Building Control told about the change.
Steels that look similar can differ in strength, stiffness and depth, which affects bearings, connections and headroom.
Next step Book a design revision (from £150 + VAT).
Who checks the temporary props before a load-bearing wall comes down?
The builder is normally responsible for temporary works, but where loads are large or the sequence unusual, an engineer should design the propping and it should be checked before the wall comes out.
A written propping arrangement means everyone knows what is holding the building up at each stage. See temporary works and propping.
Next step Book a temporary works and propping design (from £500 + VAT).
We've opened the ceiling and the joists run the opposite way to the drawings. What happens now?
Stop that part of the work and tell the engineer: the design depends on which way the joists span, so it needs checking and possibly revising before work continues.
This is common in altered London houses. A quick site photo and measurements usually let the engineer confirm or revise the design in a short time.
Next step Book a design revision (from £150 + VAT) or a site inspection (from £250 + VAT).
Can an engineer check the steelwork before the builder covers it up?
Yes: a steelwork inspection confirms the sections, bearings, padstones and connections match the design before they are hidden, and gives you a written record.
Building Control may also want to see steelwork before it is covered.
Next step Book a structural steelwork inspection (from £300 + VAT).
Our engineer has stopped responding and the build is halfway through. Can someone take over?
Yes: another engineer can review the existing design and what has been built so far, then continue the structural role, revising anything that needs it.
Gather the drawings, calculations, Building Control correspondence and site photos. Some work may need opening up if it was covered without inspection.
Next step Send us what you have; we start with a site inspection (from £250 + VAT) and review.
Do I need a structural engineer's inspection as well as a Building Control visit?
Not always: Building Control inspects at key stages to check compliance, while an engineer's inspection is worth adding for complex steelwork, uncertain ground or where the design depends on what is found on site.
Engineer inspections also give you a written record, which helps when you sell.
Next step Book a foundation inspection (from £250 + VAT) or steelwork inspection (from £300 + VAT).
References
- Approved Document A (Structure), Building Regulations 2010
- Party Wall etc. Act 1996