Cracks appeared after next door's building work. What can I do?
Record the damage now, tell your neighbour and, if the work came under the Party Wall Act, the surveyors. An independent engineer's report establishes the likely cause.
The short answer
Photograph and date the cracks now, then tell your neighbour in writing. If the work came under the Party Wall etc. Act 1996, the Act requires the building owner to make good damage the work causes, and the surveyors named in the award deal with it, using any schedule of condition taken before work started. An independent engineer's inspection, from £450 + VAT, gives you a written opinion on the likely cause.
What to do first
- Photograph each crack with a ruler beside it, and note the date.
- Mark the ends lightly in pencil so you can see if it grows.
- Do not fill or decorate yet: the cracks are evidence.
- Tell your neighbour in writing, and their builder if work is still under way.
- Find any party wall notice, award or schedule of condition you were given.
- If anything looks unsafe, keep people away and call us on 020 3818 1115.
If the work came under the Party Wall Act
Work to a shared wall, a new wall on the boundary or digging close to your foundations usually needs notice under the Party Wall etc. Act 1996. The Act requires the building owner to make good damage the work causes. Raise the damage with the surveyor or surveyors named in the award; they compare it with the schedule of condition and decide what is owed.
If no notice was served when it should have been, the protections still matter. Speak to a party wall surveyor or solicitor about your options. Our guide The Party Wall Act and structural works explains the process.
How an engineer's report helps
An independent structural engineer inspects the damage, compares it with any earlier record and gives a written opinion on the likely cause, whether it is still moving and what repairs are needed. That evidence helps the surveyors, your neighbour or an insurer reach a fair result.
- One area of damage: Specific Structural Inspection report (from £450 + VAT)
- Cracking in several places, or the cause is disputed: structural movement investigation (from £750 + VAT)
- Is it still moving? crack monitoring (from £450 + VAT)
- A formal dispute: structural expert witness report (from £2,000 + VAT)
Before the next project starts
If a neighbour is about to start work, a schedule of condition (from £350 + VAT) records your home's condition first, and a party wall structural review (from £400 + VAT) checks their engineer's design for its effect on your house.
What to send us
- Your address and postcode
- Dated photos of the cracks
- A short description of next door's work and when it happened
- Any party wall notice, award or schedule of condition
Frequently asked questions
Who pays for the engineer's report?
Under a party wall award, the surveyors decide who pays for costs connected with the work, including reasonable costs of assessing damage. Outside the Act, you normally commission the report and may seek the cost back as part of a claim. A party wall surveyor or solicitor can advise on your case.
Could the cracks have been there already?
That is exactly what a schedule of condition is for. Without one, an engineer looks at the crack pattern, how fresh the crack edges are and how they relate to the work next door to judge whether the damage is new.
Is it safe to stay in the house?
Almost always, for typical cracking. If walls are bulging, ceilings have dropped or masonry is falling, keep away from the area and call us for an urgent inspection.
References
- Party Wall etc. Act 1996, section 7 (compensation for loss or damage caused by the work)
- BRE Digest 251, Assessment of damage in low-rise buildings